An engine programme wants adjusters in the millions, with every one tested and none of them different. The chain that does that is not a scaled-up prototype line; it is built for volume from the first step.
Bar to tested part
Eight steps, and what each one has to prove
- 01 Bar
- Case hardening steel from the mill, with its certificate. The material is chosen for the case it will take and the core it will keep.
- 02 Turn and mill
- Body and plunger turned and milled in one clamping wherever the part allows it, oil holes drilled in the same setup. Every setup removed is a source of error removed with it.
- 03 Heat treat
- Case hardened, cores left tough, closed out by hardness testing on site rather than on a third-party certificate.
- 04 Finish
- Bores honed and plungers superfinished to size, on site, with the roughness tester behind the operation.
- 05 Match
- Every bore and every plunger air gauged, sorted into classes, and paired. The fit that decides the part is made deliberately, not found by chance.
- 06 Clean
- Washed to the cleanliness specification the drawing calls, because a particle on the check valve seat is a collapsed adjuster.
- 07 Assemble
- Check ball, spring, retainer and plunger spring assembled in a clean cell, with poka-yoke on the line so a missed spring cannot leave it.
- 08 Test
- Leak-down on every part, in test oil at a controlled temperature, against the specification. Then packed.
Why the chain holds at volume
The difference between a thousand and a million
- Air gauging, not sampling
- Air gauges are quick enough to measure every bore and every plunger in a batch. That is what makes matching by class possible at programme volume, and it is what turns a capability study into a confirmed result on each part.
- Control charts on the fit
- The characteristics that decide the part are charted, so a drift in the honing or the finishing is acted on as a trend rather than found as a batch of rejects.
- One clamping, fewer hands
- Turning and milling in one setup means fewer operations, fewer transfers and fewer chances for a part to be dropped or mixed. At volume, the handling operations you remove matter more than the ones you speed up.
- Finishing on site
- Honing and superfinishing in-house means the fit is under the same control plan as everything else, and a programme is not exposed to a subcontractor’s lead time.
- Test as a gate
- The leak-down rig is the last operation, not an audit. A part that has not been through it does not exist as far as despatch is concerned.
Certification and supply
The route, stated plainly
- ISO 9001:2015
- Held by Anicon Flowcontrols LLP.
- IATF 16949
- Where the programme calls for it, adjusters are supplied through Versatile Equipments Pvt Ltd under its IATF 16949 certification, with Anicon as the manufacturing and assembly arm.
- With the parts
- Dimensional reports, material certificates, hardness results, leak-down records, and PPAP where the programme requires it.
- As an assembly
- End pivot and rocker elements are supplied loose or built into the valve train assembly, on the arrangement already running for rocker arm assemblies.
Send the drawing
A clear answer inside a working day